Administrative Updates: Capital Projects Mott/Woolman

Milestones From Benchmark Construction

Mott Cottages:

  • Mobilization – Sept. 2021
  • Sitework/ Bldg Demo/ Utilities – Nov. 2021
  • Bldg #1 Constructed/Dried in – Jan. 2022
  • Final Inspection/ C.O. – Mar. 2022
  • Bldg #2 Constructed/Dried in – Jan. 2022
  • Final Inspection/ C.O. – Mar. 2022
  • Bldg #3 Constructed/Dried in – Jan. 2022
  • Final Inspection/ C.O. – Apr. 2022
  • Bldg #4 Constructed/Dried in – Feb.. 2022
  • Final Inspection/ C.O. – Apr. 2022
  • Final Sitework/Private Garages – Apr. 2022

Woolman Lodge:

  • Mobilization – Aug. 2021
  • Sitework- Bldg Demo/ Utilities – Nov. 2021
  • Bldg Constructed/Dried in – Mar. 2022
  • Interior Construction – Apr. 2022
  • Sitework – July 2022
  • Final Inspection/ C.O. – July 2022